  • CCM Diaspora Chairman Tambo Cuba Gets Key Appointment in Yayi’s 2027 Campaign Council
  • Tambolo Backs Elewide’s Mobilisation Drive, Urges CCM Members to Rally Behind Yayi
  • Lawee Takes Inclusive Governance Message to Ogun Waterside Riverine Community
  • Education Boost: Keesan Orile Baale Donates 3,000 Exercise Books, Endorses Yayi, Tella
  • Gateway Air Ready to Airlift Hajj Pilgrims — Abiodun
  • Pioneer Civil Defence College Provost, ACG Makinde Iskil Retires At 60
  • New Ogun NUJ federated chapel Chairman Pledges inclusive leadership,Better welfare
Facebook Twitter LinkedIn Pinterest RSS Instagram YouTube WhatsApp TikTok Telegram
News BarrelNews Barrel
  • Home
  • News
  • Business
  • Education
  • Health
  • Metro
  • Politics
  • Society
  • Tech
  • Sports
News BarrelNews Barrel
You are at:Home » FG sets April 30 Completion date for Lagos-Ibadan expressway , Second Niger bridge opens in may

FG sets April 30 Completion date for Lagos-Ibadan expressway , Second Niger bridge opens in may

0
By News Barrel on April 4, 2023 News

The Federal Government has announced that the construction work on Lagos Ibadan expressway will be completed by April 30 while the second Niger bridge should be fully open to traffic by May 15.

The Minister of Works and Housing Babatunde Fashola made the announcement on Tuesday while inspecting and confirming the completion of the Loko-Oweto bridge and link roads between Benue and Nasarawa States.

Concerning the second Niger bridge and the Lagos-Ibadan expressway, Fashola said: “On the Lagos-Ibadan expressway, the date we have now, and once again, I want to appeal first to commuters on that road for their continuous patience, forbearance and understanding – it is a difficult project to execute because it is perhaps one of the busiest roads in the country.

“Building through 40,000 vehicular traffic daily is not an easy undertaking, we can’t shut down the road. So, we have to also manage and divert traffic for the safety of those who are involved in the construction.

“So, I want to implore that forbearance continues because the headline date we have for completion now is the 30th of April this month. So, in barely about four weeks, 26 days, plus or minus, that road should also be fully completed, open to traffic from Lagos to Ibadan, and beyond the toll gate up to kilometer 116. That will be done by the 30th of April.

“What will be left is 9 kilometers, from kilometers 17 to 27. And the reason why that will be left is that the Oyo state government is constructing drainage across the road, and we have decided that we need the drainage because it will help address the issue of excessive flooding and climate change in Oyo state.

“But we believe that it is better to wait for them to finish that project, and then complete the remaining 9 kilometers, instead of building it now and then having them cut it up again. So, just 9 kilometers outside Ibadan is what will be left. But by the 30th of April, your end-to-end, from Lagos tollgate to the Ibadan tollgate, the road should be open on the 30th of April for traffic.

“Yesterday, we had a periodic meeting in the Office of the Chief of Staff to the President where the contractors, our team, all reviewed the challenges (on the second Niger bridge) and how to solve them.

The link road (of the second Niger bridge) that we formally opened to traffic, the date we have now is the 15th of May, as of yesterday. We are rolling out all the steps to support the contractor to see that that date is achieved.

“A lot of snag resolutions are going to start; lane marking on the bridge will soon start and erection of signages will also soon start. Just about two weeks before the end of the term, the President will be invited to the completion, and maybe any day thereafter, he will be able to fly in and do the ceremony. But by the 15th of May, the bridge should be fully open to traffic.”

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
News Barrel
  • Website
  • Facebook
  • Twitter
  • Instagram

Newsbarrelng is an independent online news outlet committed to credible journalism and responsible reporting. We cover politics, business, entertainment, sports, and social issues shaping Nigeria and the world at large. Our editorial process is guided by accuracy, fairness, and transparency. At Newsbarrelng, we believe informed citizens build a stronger society, and we strive to provide news that reflects the realities, voices, and aspirations of people.

Related Posts

APC 2027 Campaign Committee: Big Champion Akile Egbaland Named Special Duties Committee Member Alongside APC Organising Committee Figure Yemi ‘Igwe’ Adelani

Tambolo Backs Elewide’s Mobilisation Drive, Urges CCM Members to Rally Behind Yayi

Lawee Takes Inclusive Governance Message to Ogun Waterside Riverine Community

Leave A Reply Cancel Reply

About
About

News Barrel NG is an independent online news platform dedicated to delivering timely, accurate, and impactful news from Ogun State and across Nigeria.

Facebook Twitter Instagram WhatsApp
Categories
  • Business (23)
  • Education (24)
  • Entertainment (34)
  • Health (11)
  • Metro (137)
  • News (2,631)
  • Opinion/Features (15)
  • Politics (94)
  • Security (39)
  • Society (84)
  • Sports (10)
  • Tech (34)

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

© 2026 The News Barrel. Designed by FematTech.
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms & Conditions

Type above and press Enter to search. Press Esc to cancel.